Power System
Modular Data Center Solution
Improve service level and operational efficiency of power systems
Power System
Modular Data Center Solutio
Improve service level and operational efficiency of power systems
Industry Challenges
Difficulty in Centralized Management
Computer room cabinets are deployed uniformly with widely distributed sites, resulting in long inspection cycles and delayed management.
Difficulty in Unifying Standards
The computer rooms vary in scale, grade and application requirements according to different scenarios, which makes it hard to form a unified standard for construction mode.
Difficulty in Maintenance
There is a shortage of professional O&M staff. Troubleshooting is carried out only after faults occur, which cannot guarantee the normal and stable operation of each system.
Difficulty in Timely Construction
The construction mode needs to be fast, convenient and efficient.
行业挑战
管理难集中
机房机柜统一部署,站点分布较广,巡检时间长,无法及时管理。
标准难统一
机房规模根据应用不同,等级不同,应用要求不同;建设模式无法形成统一标准。
维护难进行
专业运维人员缺乏,总是事后处理,无法保障各系统正常、稳定运行。
建设难及时
建设模式要求快速、便捷、高效。
Industry Challenges
Centralized Management Difficulties
With racks deployed across wide sites, site inspections take long and real-time management cannot be achieved.
Unified Standards Hard to Achieve
Data centers vary in scale, grade and application requirements, making it difficult to unify construction standards.
Difficult Maintenance
Lack of professional maintenance staff leads to remedial handling only, which fails to guarantee stable operation of each system.
Industry Cases
Project case presentation of State Grid Heilongjiang (Shuangyashan) Electric Power Co., Ltd
Project Background
Construction of new office building of State Grid Heilongjiang (Shuangyashan) Electric Power Co., Ltd. The computer room serves as the new data room for State Grid (Shuangyashan) Power Dispatching & Control Center, with a construction area of 260 square meters.
Project Overview
1. Adopt DTCT modular computer room cold aisle products: 2 sets of double-row cold aisle modular data centers, 30 cabinets per set, total 60 cabinets including 4 power distribution cabinets. Main components include modular cabinets, aisle sliding doors, flip skylights, 18-position PDU power supplies, trays and brackets, cabinet grounding copper bars, etc.; 6 ordinary cabinets for supporting large screens in command & control center and small monitoring room.
2. Environmental monitoring system: DTCT provides complete power and environment monitoring products matching the modular cold aisle system.
Case presentation of the third phase of Zhejiang Energy Yueqing Power Plant project
Project Background
Zheneng Yueqing Power Plant Project is invested and constructed by Zhejiang Energy Group Co., Ltd. as a key project of Zhejiang Provincial Government. The plant is located in the area of Nanyue Town and Puqi Town on the west bank of Yueqing Bay, 20 km from Yueqing downtown and 40 km from Wenzhou. On June 13, 2023, Unit 6 of Phase III of Zheneng Yueqing Power Plant, a major project under Zhejiang's "Thousand Projects & Trillion Investment" Initiative, passed the 168-hour full-load trial operation and was officially put into service, marking the full completion and commissioning of Phase III.
Project Overview
This project adopts DTCT new-generation integrated modular micro data center products, including two sets of 10-in-1 units and one set of 3-in-1 unit, together with supporting power & environment monitoring software system.
Case Presentation of Guoneng Zhejiang Beilun No. 3 Power Generation Co., Ltd. Project
Project Background
Guoneng Zhejiang Beilun No.3 Power Generation Co., Ltd. was founded on December 31, 2006. It belongs to the power and heat production & supply industry. Its business scope covers power generation (operated within the validity period of license), construction of domestic thermal power plants and heat supply.
Project Overview
This project adopts DTCT new-generation full-range modular data center products, including 75 IT cabinets, 4 network wiring cabinets, 4 integrated power distribution cabinets and 10 in-row air conditioners to build 2 cold aisles of 1.2m width and 2.6m height (including skylight flip height), forming double-row cold aisle modular computer room. It is equipped with 12 sets of 50kVA modular power modules, 480 units of 200AH lead-acid batteries and 3 power distribution cabinets.
Industry Cases
Project case presentation of State Grid Heilongjiang (Shuangyashan) Electric Power Co., Ltd
Project Background
This project refers to the construction of a new office building of State Grid Heilongjiang (Shuangyashan) Electric Power Co., Ltd. The computer room serves as the new data room of State Grid (Shuangyashan) Power Dispatching and Control Center, with a building area of 260 square meters.
Project Overview
1. Adopt DTCT Deltasent modular computer room cold aisle products: 2 sets of double-row cold aisle modular data center products, 30 cabinets per set, totaling 60 cabinets including 4 power distribution cabinets. Main components include modular cabinets, aisle sliding doors, flip skylights, 18-position PDU power supplies, trays and brackets, cabinet internal grounding copper bars, etc.; 6 ordinary cabinets to support the large screen of command & control center and small monitoring room;
2. Power & environment monitoring system: Deltasent can provide complete basic power and environment monitoring products to match the modular cold aisle system.
Case presentation of the third phase of Zhejiang Energy Yueqing Power Plant project
Project Background
Zheneng Yueqing Power Plant Project is invested and constructed under the holding of Zhejiang Energy Group Co., Ltd., and listed as a key project by Zhejiang Provincial Government. The plant site is located in the area of Nanyue Town and Puqi Town in Yueqing, on the west bank of Yueqing Bay, 20 km from downtown Yueqing and 40 km from Wenzhou. On June 13, 2023, Unit 6 of Phase III Project of Zheneng Yueqing Power Plant, one of Zhejiang's "Thousand Projects & Trillion Investment" major projects, passed the 168-hour full-load trial operation and was officially put into service. So far, Phase III Project of Yueqing Power Plant has been fully completed and commissioned.
Project Overview
This project adopts Deltasent new-generation integrated modular micro data room product series, including two sets of ten-units and one set of three-units, together with supporting power & environment monitoring software system.
Case Presentation of Guoneng Zhejiang Beilun No. 3 Power Generation Co., Ltd. Project
Project Background
Guoneng Zhejiang Beilun No.3 Power Generation Co., Ltd. was founded on December 31, 2006. It belongs to the electric power and heat production & supply industry. Its business scope includes power generation (operate within the validity period of license), construction of domestic thermal power plants and heat supply services.
Project Overview
This project adopts the full range of Deltasent new-generation modular data center products, including 75 IT equipment cabinets, 4 network wiring cabinets and 4 integrated power distribution cabinets. 10 in-row air conditioners form two 1.2m-wide cold pools with a height of 2.6m (including skylight flip height), constituting a double-row cold pool modular computer room. It is equipped with 12 sets of 50kVA modular power modules, 480 units of 200AH lead-acid batteries and 3 power distribution cabinets.
Solution Value
Flexible Deployment
Build computer rooms of corresponding grades according to different data volumes and business systems to meet overall application requirements.
Convenient Maintenance
Supports remote centralized control to realize vertical architecture deployment and unified management.
Efficient Management
Optimize the overall maintenance design of the computer room. Effective management is realized via software to reduce ineffective inspections and improve inspection efficiency.
Energy Saving & Low Carbon
Modular construction, green energy-saving, high efficiency and convenience.
Solution Value
Flexible Deployment
Build computer rooms of corresponding grades according to data volume and business systems to meet overall application requirements.
Easy Maintenance
It supports remote centralized control to realize vertical architecture deployment and unified management.
Efficient Management
Optimize the overall maintenance design of the computer room. Effective management is realized via software to eliminate unnecessary inspections and improve patrol efficiency.
Energy Saving & Low Carbon
Modular construction, green energy saving, high efficiency and convenience.
Power System Cooperation Cases